Job Bid Calculator: How to Price a Job With Overhead and Profit

FREE TOOL FOR CONTRACTORS

Bid Every Job to Cover Your Costs and Make a Profit

Busy all year and still short on cash usually means the bids are too low. Here is the math that fixes it.

The formula

Bid price = (Direct costs + Overhead) / (1 – Profit margin)

  • Direct costs are what this job alone costs: materials, labor, subs, equipment, permits, dump fees.
  • Overhead is this job’s share of what you pay to stay in business: insurance, trucks, office, software, your time estimating.
  • Profit margin is what is left over as a percent of the price.

Step 1: Find your overhead percentage

Take last year’s overhead and divide it by last year’s direct job costs. If you spent $90,000 on overhead and $600,000 on direct job costs, your overhead rate is 15%. Every job needs to carry 15% on top of its direct costs just to break even. If your books are not clean enough to pull those two numbers, that is the first thing to fix.

Step 2: Price the job

Materials$8,000
Labor: 120 hours at $55 burdened$6,600
Subcontractors$3,000
Equipment, permits, dump fees$800
Total direct cost$18,400
Overhead at 15%$2,760
Bid price for a 10% net profit$23,511
Net profit$2,351
Markup on direct cost27.8%

“Burdened” labor means the wage plus payroll taxes and workers comp. Bidding at the bare wage is one of the quietest ways to lose money on every job.

Why “10 and 10” falls short

Many contractors add 10% for overhead and 10% for profit. On the same job, that gives $18,400 x 1.10 x 1.10 = $22,264. With real overhead at 15%, the profit is only $1,104, a 5.0% margin. You think you are making 10% and you are making half that. On a $1 million year, that gap is about $50,000.

10 and 10Priced from your real overhead
Bid price$22,264$23,511
Net profit$1,104$2,351
Net margin5.0%10.0%

Step 3: Check the job after it is done

A bid is a guess. Job costing tells you whether the guess was right. Track actual labor, materials, and subs against each job so the next bid is sharper. Our bookkeeping for contractors sets that up for you.

Free download: the bid calculator in Excel

Five calculators in one workbook: job bid, hourly rate, markup and margin, break-even, and rental cash flow. Type in your numbers and the answers update. Works in Excel and Google Sheets. No email required.

Common questions

What is a normal overhead percentage for a contractor?

It varies widely by trade and size, so use your own. A one-truck operation and a 20-person firm with an office have very different overhead. Your books from last year are the most reliable source.

Should overhead be a percent of direct costs or of labor?

Either works if you are consistent. Percent of direct cost is simplest. If your jobs swing between material-heavy and labor-heavy, spreading overhead by labor hours can be more accurate.

What about contingency?

Add it as its own line in direct costs for jobs with real unknowns, like older homes or tight schedules, rather than padding your profit number.

Know Which Jobs Actually Make Money

We clean up the books, set your real overhead rate, and set up job costing so every bid is built on facts. Free 20-minute call.